Search Results
Elevator out of service at 24th St. Mission Station 6/14/21-7/22/21
UPDATE: July 19, 2021 The new projected return to service date for the 24th St. Mission street level elevator is July 22, 2021. The delay was caused by severe corrosion discovered during the door replacement project. The corrosion requires crews to chip out the existing concrete, reinstall new brackets under
Dublin/Pleasanton Station garage closed for lighting improvements starting 9/7
On Tuesday, September 7, 2021, the garage at Dublin/Pleasanton Station will be closed in phases for approximately eight weeks to allow our contractor to retrofit and upgrade the garage lighting. Level 1 will remain open during Phase 1 of the project. Levels 2-4 will be open during Phase 2. Surface lots will
South San Francisco Station garage closed for lighting improvements starting 8/30
On Monday, August 30, 2021, the garage at South San Francisco Station will be closed for approximately six weeks to allow our contractor to retrofit and upgrade the garage lighting. Levels 2-4 will remain open during Phase 1 of the project. Level 1 will be open during Phase 2. Surface lots will also remain
MacArthur Station garage closed in phases for lighting improvements starting 12/7/2021
On Tuesday, December 7, 2021, the garage at MacArthur Station will be closed in phases for approximately five weeks to allow our contractor to retrofit and upgrade the garage lighting. During Phase 1, floors 1 and 2 of the garage will be closed with parking available on floors 3 and up. Once floors 1 and 2
Access impacts expected at North Berkeley Station from work on raised crosswalk
Work is scheduled to begin on July 5, 2022, on a raised crosswalk in front of the North Berkeley Station. Work will take place directly in front of the station entrance (see map). This is the latest step for the North Berkeley Access Improvements Project. Construction impacts will include the following
Temporary relocation of bike lockers at Daly City due to earthquake safety work
Dear Customer: As part of our system-wide Earthquake Safety Program, we have begun strengthening structures at the Daly City Station to withstand future earthquakes. The work requires temporary relocation of some of the bicycle lockers and bicycle racks. Lockers and racks will be closed on Monday, August 9
City of El Cerrito paving project to affect parking at stations
On Monday, September 28th, the City of El Cerrito (City) began its citywide street repaving project that will affect street parking nearby the El Cerrito del Norte and El Cerrito Plaza stations. City staff has advised BART that the repaving project is a two-step process that will prohibit parking on the
Earthquake safety work in Rockridge parking lot
As part of our systemwide Earthquake Safety Program, we will be strengthening structures at Rockridge Station to better withstand future earthquakes. Starting September 23, we will begin reinforcing the support columns under our tracks with a fiber-reinforced polymer (FPR) material which will be wrapped
Board awards contract for Powell St. Station modernization
The BART Board today authorized the General Manager to award an $11.3 million contract to modernize Powell St. Station. The modernization includes reconfiguring and reopening bathrooms at the station, moving ticket vending machines in the middle of the concourse near the entrance to Westfield San Francisco
Elevators out at Daly City Station 4/17-5/5 (Update)
4/28/2017: 2nd Update, The floors have been replaced successfully, however, both elevator doors are experiencing mechanical problems and so the elevators will need to be out of service for another week. 4/18/2017--Update: Due to unexpected issues discovered when removing the old flooring, this work will take