Earthquake Safety construction work inside Fruitvale Station

As part of BART’s systemwide Earthquake Safety Program, seismic retrofit work at the Fruitvale Station continues. STAGE ONE (1) earthquake safety construction activity has begun inside the Fruitvale Station on the south side (back end) of the concourse -- this is a change from the original plan of working

K9 Unit

The safety and security of the BART system and its riders, employees, and surrounding communities are paramount concerns of BART PD. One vital tool that the Department has to keep the public safe and secure is its police canines. All BART PD canines are trained in explosives detection. K-9 teams deter crime

Six years of police reforms

Six years after the tragic shooting death of Oscar Grant III focused attention on the BART Police Department (BPD), BART and BPD continue their efforts to reshape and reform themselves to meet the needs of the community BART serves. Among the steps BART took immediately after the January 1, 2009 tragedy was

Station Profile Survey running through May will gather vital data

The granddaddy of all BART research surveys -- known as the Station Profile Survey -- is gearing up to begin Feb. 17 and will provide a treasure trove of data to guide the agency and help the public in the future. It's the largest and oldest of all BART surveys, done approximately every six-to-10 years since

Electrical upgrade construction to begin at Ashby Station

As part of our 34.5KV cable system upgrade project, construction will begin to install electrical auxiliary cables and supports between MacArthur and Ashby stations and along elevated structures in north Oakland. Construction crews will create fenced enclosures to install cables, electrical switchgear and

Earthquake safety work at Daly City Station to affect fare gates

Dear Customer: As part of BART's systemwide Earthquake Safety Program, we have been strengthening structures at the Daly City Station to withstand future earthquakes. Starting early February 2010, construction crews will start work inside the station. We will need to close two fare gates at the south end of

Apology to our valued customers

On Tuesday, March 30, we experienced a small fire between the Powell Street and Civic Center stations during the heart of the morning commute. The fire forced us to suspend train service into San Francisco. We worked quickly to put out the flames. After we restored train service, we began making announcements

Temporary elevator closures at 12th, 19th, MacArthur for ADA work

Dear Customer: As part of work to upgrade our stations and improve Americans with Disabilities Act compliance, we will be temporarily closing some elevators at three stations over the next several weeks: 12th St./Oakland City Center Station; 19th St./Oakland Station and MacArthur Station Details on each